Project Overview
Project Purpose
- Widen University Avenue
- Construction of new curb, gutter and sidewalks
- Construction of multi-use path
- Construction of storm drain
- Permanent signs and roadway striping
- New lighting
- Railroad crossings

Updates
CREWS TO CLOSE NM 101 (UNIVERSITY AVE.) AT LAGUNA LATERAL
Thursday, December 12, 2024
Construction Begins Tuesday, Nov. 26 on Project to Widen University Ave/NM 101. From Avenida de Mesilla to South Main Street
Details
Phase 1A – Mesilla Intersection Ramps
Phase 1A, 1B and 1C are expected to last through May 2025
Crews will:
- Install signs at the beginning and end of project and two variable message signs within the project.
- Build the Avenida de Mesilla intersection ramps at University.
- Install temporary traffic signals.
Phase 1B – Road Closure at Laguna Lateral
Crews will:
- Construct entire Laguna Lateral hydraulic structure and irrigation channel and storm drainpipes.
- All traffic routes will be closed across the Laguna Lateral.
- Detour will be in place along Avenida de Mesilla, West Lincoln Avenue and South Main Street.
- Plans
Phase 1C – North Detour Pavement Widening
Crews will:
- Install detours to begin widening part of the northern portion of University.
- Two-way traffic will remain on existing lanes during nonworking hours.
- A flagger will be on-site as needed to direct one-way traffic during paving operations.
- A detour will be in place and will be provided in advance.
- Plans
Phase 2 – South of Centerline Construction
This phase is expected to last through November 2025.
Crews will:
- Build all remaining infrastructure south of the centerline from the beginning of the project to the railroad
- Build and connect college lateral upgrades and build half of the perpendicular storm drainage pipeline.
- All eastbound traffic on University will be detoured to McDowell and Bowman.
- Plans
Phase 3A – North of Centerline Construction
Phase 3 is expected to last from November 2025 to Summer 2026.
Phase 3 Plans
Crews will:
- Install asphalt pavement north of the construction centerline from the beginning of the project to the railroad and will build and connect the remaining storm drainage pipeline.
- Eastbound traffic on University will be open and westbound traffic will be closed with a one-way eastbound detour.
- Detours will be to Teresita and Boldt Street and to Old Farm and Stanford to build each turnout.
Phase 3B – Road Closure at Railroad Crossing
Crews will:
- Build the infrastructure at the railroad, including ramps and signal operation.
- All traffic will be closed from Bowman to Main Street with a detour.
Phase 3C – Main Street Median Construction
Crews will:
- Remove part of the median and rebuild the median nose.
- Two-way traffic will be opened on University.
Phase 4 – Final Phase
Phase 4 is expected to last from summer to fall of 2026.
Crews will
- Install any remaining asphalt pavement, finish striping the roadway and install permanent signage.
- Temporary lane closures may be required.
Comment Form - University Ave Multimodal Project, CN LC00290
CN LC00290