University Avenue NM 101 Multimodal Project

  1. Home
  2. University Avenue NM 101 Multimodal Project

County

Dona Ana

District

District 1

STIP Number

Status

Construction

Patti Watson
Communications Contractor, CWA Strategic Communications
Office: 505-245-3134
Cell: 505-269-9691
1-800-687-3417
pattiw@cwastrategic.com

Gareth Bill
Communications Contractor, CWA Strategic Communications
Office: 505-245-3138
Cell: 505-417-9989
gareth@cwastrategic.com

Ami Evans
NMDOT Public Information Officer District One
Cell: 575-640-5981
ami.evans@dot.nm.gov

Project Overview

Project Purpose

  • Widen University Avenue
  • Construction of new curb, gutter and sidewalks
  • Construction of multi-use path
  • Construction of storm drain
  • Permanent signs and roadway striping
  • New lighting
  • Railroad crossings

Updates

CREWS TO PAVE EASTBOUND NM 101 BETWEEN AVENIDA DE MESILLA AND SOUTH MAIN STREET FROM TUESDAY, DECEMBER 9, 2025-WEDNESDAY, DECEMBER 17, 2025

Traffic Impacts

During paving, crews will be paving NM 101 as well as turnouts located at each intersection of NM 101 and side streets.

Motorists in the area should expect delays and be patient if paving trucks are blocking intersections.

NOTES: Crews will pave the intersection of Boldt Street and NM 101 and Teresita Street and NM 101 on different days so access will be provided to homes in the area.

Crews will also pave the intersections of Old Farm and NM 101 and Stanford and NM 101 on different days so access will be provided to homes in the area.

Regular work hours are Monday-Friday 7 a.m.-4:30 p.m. although the contractor may work longer hours or on weekends as needed. Additional construction will follow this phase, with the project expected to be completed in fall 2026. All construction is weather permitting and is subject to change without notice.

    Details

    University Avenue Corridor Study Phase B | Detailed Evaluation of Alternatives

    Phase 1A – Mesilla Intersection Ramps

    Phase 1A, 1B and 1C are expected to last through May 2025

    Crews will:

    • Install signs at the beginning and end of project and two variable message signs within the project.
    • Build the Avenida de Mesilla intersection ramps at University.
    • Install temporary traffic signals.

    Phase 1B – Road Closure at Laguna Lateral

    Crews will:

    • Construct entire Laguna Lateral hydraulic structure and irrigation channel and storm drainpipes.
    • All traffic routes will be closed across the Laguna Lateral.
    • Detour will be in place along Avenida de Mesilla, West Lincoln Avenue and South Main Street.
    • Plans

    Phase 1C – North Detour Pavement Widening

    Crews will:

    • Install detours to begin widening part of the northern portion of University.
    • Two-way traffic will remain on existing lanes during nonworking hours.
    • A flagger will be on-site as needed to direct one-way traffic during paving operations.
    • A detour will be in place and will be provided in advance.
    • Plans

    Phase 2 – South of Centerline Construction

    This phase is expected to last through November 2025.

    Crews will:

    • Build all remaining infrastructure south of the centerline from the beginning of the project to the railroad
    • Build and connect college lateral upgrades and build half of the perpendicular storm drainage pipeline.
    • All eastbound traffic on University will be detoured to McDowell and Bowman.
    • Plans

    Phase 3A – North of Centerline Construction

    Phase 3 is expected to last from November 2025 to Summer 2026.
    Phase 3 Plans

    Crews will:

    • Install asphalt pavement north of the construction centerline from the beginning of the project to the railroad and will build and connect the remaining storm drainage pipeline.
    • Eastbound traffic on University will be open and westbound traffic will be closed with a one-way eastbound detour.
    • Detours will be to Teresita and Boldt Street and to Old Farm and Stanford to build each turnout.

    Phase 3B – Road Closure at Railroad Crossing

    Crews will:

    • Build the infrastructure at the railroad, including ramps and signal operation.
    • All traffic will be closed from Bowman to Main Street with a detour.

    Phase 3C – Main Street Median Construction

    Crews will:

    • Remove part of the median and rebuild the median nose.
    • Two-way traffic will be opened on University.

    Phase 4 – Final Phase

    Phase 4 is expected to last from summer to fall of 2026.

    Crews will

    • Install any remaining asphalt pavement, finish striping the roadway and install permanent signage.
    • Temporary lane closures may be required.

    Project Maps and Plans

    Road Closures and Phases Maps

    Phase 1B

    Phase 1C

    Phase 2

    Phase 3

    Comment Form - University Ave Multimodal Project, CN LC00290

    CN LC00290

    This field is for validation purposes and should be left unchanged.
    Email is optional; but if you do provide your email address, we can add you to the mailing list.