Project Overview
Project Purpose
- Widen University Avenue
- Construction of new curb, gutter and sidewalks
- Construction of multi-use path
- Construction of storm drain
- Permanent signs and roadway striping
- New lighting
- Railroad crossings

Updates
REMINDER: BOWMAN AVENUE TO BE CLOSED BETWEEN NM STATE ROAD 101 (UNIVERSITY AVE.) AND WEST UNION AVENUE THRU FRIDAY, AUGUST 1 AND OCCASIONALLY FOR ABOUT THE NEXT MONTH; LOCAL TRAFFIC CAN USE MCDOWELL ROAD AS DETOUR; OTHER TRAFFIC ASKED TO SEEK AN ALTERNATE ROUTE
REMINDER: Crews have closed Bowman Avenue through Friday, August 1, 2025, and will be closing the roadway occasionally for about the next month (through late August 2025), as they work on the turnout and roadway paving.
Detours:
- Local traffic from Capri Road and West Conway Avenue can use McDowell Road as a detour route.
- Traffic on College Avenue can use S. Main Street.
- Other traffic should seek an alternate route
Details
Phase 1A – Mesilla Intersection Ramps
Phase 1A, 1B and 1C are expected to last through May 2025
Crews will:
- Install signs at the beginning and end of project and two variable message signs within the project.
- Build the Avenida de Mesilla intersection ramps at University.
- Install temporary traffic signals.
Phase 1B – Road Closure at Laguna Lateral
Crews will:
- Construct entire Laguna Lateral hydraulic structure and irrigation channel and storm drainpipes.
- All traffic routes will be closed across the Laguna Lateral.
- Detour will be in place along Avenida de Mesilla, West Lincoln Avenue and South Main Street.
- Plans
Phase 1C – North Detour Pavement Widening
Crews will:
- Install detours to begin widening part of the northern portion of University.
- Two-way traffic will remain on existing lanes during nonworking hours.
- A flagger will be on-site as needed to direct one-way traffic during paving operations.
- A detour will be in place and will be provided in advance.
- Plans
Phase 2 – South of Centerline Construction
This phase is expected to last through November 2025.
Crews will:
- Build all remaining infrastructure south of the centerline from the beginning of the project to the railroad
- Build and connect college lateral upgrades and build half of the perpendicular storm drainage pipeline.
- All eastbound traffic on University will be detoured to McDowell and Bowman.
- Plans
Phase 3A – North of Centerline Construction
Phase 3 is expected to last from November 2025 to Summer 2026.
Phase 3 Plans
Crews will:
- Install asphalt pavement north of the construction centerline from the beginning of the project to the railroad and will build and connect the remaining storm drainage pipeline.
- Eastbound traffic on University will be open and westbound traffic will be closed with a one-way eastbound detour.
- Detours will be to Teresita and Boldt Street and to Old Farm and Stanford to build each turnout.
Phase 3B – Road Closure at Railroad Crossing
Crews will:
- Build the infrastructure at the railroad, including ramps and signal operation.
- All traffic will be closed from Bowman to Main Street with a detour.
Phase 3C – Main Street Median Construction
Crews will:
- Remove part of the median and rebuild the median nose.
- Two-way traffic will be opened on University.
Phase 4 – Final Phase
Phase 4 is expected to last from summer to fall of 2026.
Crews will
- Install any remaining asphalt pavement, finish striping the roadway and install permanent signage.
- Temporary lane closures may be required.
Comment Form - University Ave Multimodal Project, CN LC00290