University Avenue NM 101 Multimodal Project

  1. Home
  2. University Avenue NM 101 Multimodal Project

County

Dona Ana

District

District 1

STIP Number

Status

Construction

Patti Watson
Communications Contractor, CWA Strategic Communications
Office: 505-245-3134
Cell: 505-269-9691
1-800-687-3417
pattiw@cwastrategic.com

Ami Evans
NMDOT Public Information Officer District One
Cell: 575-640-5981
ami.evans@dot.nm.gov

Project Overview

Project Purpose

  • Widen University Avenue
  • Construction of new curb, gutter and sidewalks
  • Construction of multi-use path
  • Construction of storm drain
  • Permanent signs and roadway striping
  • New lighting
  • Railroad crossings

Updates

CREWS HAVE RESUMED WORK ON PHASE 3 OF PROJECT ON NM 101 (UNIVERSITY AVENUE); ONLY ONE LANE OF TRAFFIC IS OPEN EASTBOUND BETWEEN AVENIDA DE MESILLA AND SOUTH MAIN STREET

Update as of Monday, January 5, 2026

As of Monday, January 5, 2026, crews have resumed construction on Phase 3 of the project to widen NM 101 (University Ave) from Avenida de Mesilla to South Main Street and build storm drainage and a new multi-use path.

Traffic Impacts

The following traffic impacts are now in place:

  • Only one lane of eastbound traffic will be open on NM 101 (University Ave) between Avenida de Mesilla and S Main Street
  • Traffic heading westbound is detoured to W Union Ave. 

Access will be maintained to all residences and Zia Middle School.

This phase is expected to last through late January or early February 2026. Additional construction phases will follow, with the project expected to be completed in fall 2026.

Regular work hours are Monday-Friday 7 a.m.-4:30 p.m. although the contractor may work longer hours or on weekends as needed. All construction is weather permitting and is subject to change without notice.

For more information visit https://www.dot.nm.gov/universitynm101/ or wwwnmroads.com.

To sign up for free construction updates, contact Patti Watson (information listed above).

Details

University Avenue Corridor Study Phase B | Detailed Evaluation of Alternatives

Phase 1A – Mesilla Intersection Ramps

Phase 1A, 1B and 1C are expected to last through May 2025

Crews will:

  • Install signs at the beginning and end of project and two variable message signs within the project.
  • Build the Avenida de Mesilla intersection ramps at University.
  • Install temporary traffic signals.

Phase 1B – Road Closure at Laguna Lateral

Crews will:

  • Construct entire Laguna Lateral hydraulic structure and irrigation channel and storm drainpipes.
  • All traffic routes will be closed across the Laguna Lateral.
  • Detour will be in place along Avenida de Mesilla, West Lincoln Avenue and South Main Street.
  • Plans

Phase 1C – North Detour Pavement Widening

Crews will:

  • Install detours to begin widening part of the northern portion of University.
  • Two-way traffic will remain on existing lanes during nonworking hours.
  • A flagger will be on-site as needed to direct one-way traffic during paving operations.
  • A detour will be in place and will be provided in advance.
  • Plans

Phase 2 – South of Centerline Construction

This phase is expected to last through November 2025.

Crews will:

  • Build all remaining infrastructure south of the centerline from the beginning of the project to the railroad
  • Build and connect college lateral upgrades and build half of the perpendicular storm drainage pipeline.
  • All eastbound traffic on University will be detoured to McDowell and Bowman.
  • Plans

Phase 3A – North of Centerline Construction

Phase 3 is expected to last from November 2025 to Summer 2026.
Phase 3 Plans

Crews will:

  • Install asphalt pavement north of the construction centerline from the beginning of the project to the railroad and will build and connect the remaining storm drainage pipeline.
  • Eastbound traffic on University will be open and westbound traffic will be closed with a one-way eastbound detour.
  • Detours will be to Teresita and Boldt Street and to Old Farm and Stanford to build each turnout.

Phase 3B – Road Closure at Railroad Crossing

Crews will:

  • Build the infrastructure at the railroad, including ramps and signal operation.
  • All traffic will be closed from Bowman to Main Street with a detour.

Phase 3C – Main Street Median Construction

Crews will:

  • Remove part of the median and rebuild the median nose.
  • Two-way traffic will be opened on University.

Phase 4 – Final Phase

Phase 4 is expected to last from summer to fall of 2026.

Crews will

  • Install any remaining asphalt pavement, finish striping the roadway and install permanent signage.
  • Temporary lane closures may be required.

Project Maps and Plans

Road Closures and Phases Maps

Phase 1B

Phase 1C

Phase 2

Phase 3

Comment Form - University Ave Multimodal Project, CN LC00290

CN LC00290

This field is for validation purposes and should be left unchanged.
Email is optional; but if you do provide your email address, we can add you to the mailing list.