NM 213 AND NM 404

Construction is scheduled to resume on two projects to reconstruct and improve 3.38 miles of NM 213 and NM 404 near the Texas state line on Monday, Sept. 21, 2026.

County

Doña Ana

District

District 1

STIP Number

E100321/E100322

Status

Construction Phase

Contact

Bernard Posada
Construction Project Manager
575-545-2948

Project Overview

WORK ON NM 213 and NM 404 INCLUDES:

  • Reconstruction and widening of NM 213 as a four-lane divided highway with frontage roads from the Texas state line to milepost 2.21.
  • Reconstruction of NM 404 from Milepost 8.813 to Milepost 8.9 at the intersection of NM 404 and NM 213.
  • New bridge construction and new bypass lanes for local traffic.
  • 65-mile-per-hour ramps for both north-to-west and east-to-south traffic at the new intersection of NM 213 and NM 404.
  • A new diamond interchange at NM 213 and County Road A74.
NM 213/NM 404 Interchange Project
NM 213 NM 404 Interchange Project

CONSTRUCTION PROGRESS

CREWS TO CONTINUE WORKING ON WEST SIDE OF NM 213 AND INSIDE LANES OF NM 404 WEST OF ROUNDABOUT

Construction is continuing on reconstruction of and improvements to  NM 404 and NM 213 from the roundabout to near the Texas state line. Crews will continue to implement temporary flagging and mobile traffic control as needed.

Traffic Impacts

Weeks of October 26-30, 2026:

  • Crews will push eastbound and westbound traffic on NM 404 to the inside lanes about a mile west of the roundabout. There will only be one lane of traffic open in each direction (eastbound and westbound) west of the roundabout for about four months, through about February 2027, as crews work on Phase one of construction.
  • Crews are continuing installation of fencing and guardrails. as well as preparing for new bridge construction and MSE (mechanically stabilized earth) walls.

NOTE: The speed limit will be reduced to 45 mph throughout the construction zone for the safety of traveling motorists.

FULL CONSTRUCTION UPDATE

Project Timeline and Funding

Timeline

September 2026 to Summer 2028

Construction on the total project is expected to last about 21 months, through summer 2028.

All construction is weather permitted and it is subject to change without notice.

Funding

Federal $83,739,234

Stay in the loop during construction!

If you’d like to receive construction updates, please email Patti Watson at pattiw@cwastrategic.com and she’ll be happy to add you to the list.

For more information, you can reach Patti directly at 505‑245‑3134, on her cell at 505‑269‑9691, or toll‑free at 1‑800‑687‑3417.